Projects

99 Bishopsgate

Category: Mechanical Inspection
Client: EdenMEC / Deutsche Bank

Technical Systems Validation

Following end-user complaints of office temperatures, a survey was undertaken to establish the condition of the 4-pipe fan coil unit system installed throughout the floor by a previous contractor.

Due to the financially sensitive nature of the tenant's work, all surveys had to be undertaken out of working hours and collated into a final condition report.

Key Deliverables:
  • Photographic Survey
  • Written Condition Report
  • Identification of CHW Circuit
  • Recommendations
  • FCU's Referenced on Drawing

This project was made more challenging by multiple Chilled Water circuits on the floor, with a Critical Circuit requiring constant continity of service. IsoDome are available to undertake MEP systems validation work, including out-of-hours inspection and reporting.